Case study: a staged change of box supplier in series production (approx. 150 SKUs)

A manufacturer of products for the construction industry from the Lublin region (over 400 employees, revenue above PLN 100 million) is handing over its box supply to us in stages: ultimately approx. 150 SKUs, taken over in full, one after another, following product approval to VDA. We produce and stock about half of the SKUs, and the other half, with a very low annual volume, we produce only after receiving an order. Orders from the customer’s SAP system are read automatically from PDF files, an order placed in the morning is fulfilled the same day, and every morning one run by our own vehicle delivers 4–8 pallet spaces straight to the line, in a sequence that follows the customer’s production plan.

This description is anonymised: we do not give the company’s name, the location of the plant or the type of products. Status as at November 2026.

The customer described operates in Poland. Delivery within 24 hours of call-off applies to our own transport within Poland; to customers abroad we ship pallets by freight forwarder or as a full truckload, and the delivery schedule is agreed in the quotation.

The case in brief

Customer manufacturer of products for the construction industry from the Lublin region; over 400 employees; revenue above PLN 100 million
Scope ultimately approx. 150 box SKUs
Takeover method whole SKUs, one after another, starting with the problematic ones; the incumbent supplier serves the SKUs that have not yet moved to us
Supply model about half of the SKUs: production and stockholding (on average approx. one quarter’s consumption, depending on the SKU); about half: made to order at a very low annual volume, from a stock of board sheets
Quality the customer’s minimum requirements met before the audit; customer audit to VDA guidelines with no findings; each SKU: reference samples, measurement report, inspection sheet, sign-off before the first delivery
Integration orders from the customer’s SAP as PDFs by email, read automatically; WZ delivery notes and labels with barcodes; accounting documents by email and via KSeF (Poland’s national e-invoicing system) in the form specified by the customer
Deliveries order in the morning, production the same day, delivery the next morning; one run a day by our own vehicle, 4–8 pallet spaces, straight to the line, in the sequence of the customer’s production plan
Difficulties and solutions low box in thick BC board: samples without creasing matrices did not pass, so we bought a machine that works with creasing matrices; labels and WZ delivery notes: customer numbers added and unique print templates for handheld scanners
Results (status as at November 2026) deliveries without delays; not a single complaint since deliveries began; thanks to just-in-time deliveries the customer ran down its own buffer and gave up a rented warehouse

The starting point: three customer expectations

The customer was looking for a supplier that would meet three expectations:

  • Price. The price criterion was one of the reasons for the change; we do not disclose the commercial terms.
  • Just-in-time deliveries. The incumbent supplier fulfilled orders within a few days, so the customer kept its own buffer of boxes. The buffer required additional, rented warehouse space, which the customer wanted to use for other purposes. This affected its total cost.
  • Stable quality and a fast response to issues raised. The customer expected repeatable quality and efficient complaint handling.

Two types of SKU

Of the approx. 150 SKUs, we produce and stock about half. We set the stock level separately for each SKU on the basis of consumption; on average it is about one quarter’s consumption, and the quantities are monitored by our system (some SKUs have differently defined rules). The rules for storing and invoicing the stock are set out in the contract.

The other half consists of SKUs with a very low annual volume. We do not stock them as finished boxes: we produce them after receiving an order, from a stock of board sheets managed by our system. Every production order contains clear production instructions.

Audit and product approval to VDA

Before the audit the customer gave us its minimum requirements for a supplier, covering among other things quality assessment, the methods of assessing it and the complaints register. We met them, and the audit carried out by the customer according to VDA guidelines closed with no findings. VDA is a method of auditing and assessing a supplier, not a certificate; we write more about it in our guide to auditing a packaging supplier.

Each SKU went through approval before the first delivery: reference samples, measurement report, inspection sheet and sign-off. At the sample approval stage we made changes (described below, in the section ‘What did not work the first time’). Since deliveries began the customer has not raised a single complaint.

SAP integration and documents

Orders generated in the customer’s SAP reach us by email as PDF files. Our system reads them automatically; we built the automation ourselves. For every delivery we automatically generate a WZ delivery note with barcodes, plus pallet and product labels with codes and the customer’s order numbers. The customer’s warehouse scans them automatically, which speeds up its work. We send advance notice of every delivery. We send accounting documents by email and via KSeF, in the form specified by the customer.

Deliveries: daily, straight to the line

How one delivery runs:

  1. In the morning an order arrives (a PDF from the customer’s SAP), which our system reads automatically.
  2. The same day we produce it from the sheet stock or pick it from the warehouse.
  3. We generate a WZ delivery note with barcodes, plus pallet and product labels with the customer’s order numbers.
  4. We arrange the pallets in the sequence that follows the customer’s production plan and send advance notice of the delivery.
  5. The next morning one run by our own vehicle delivers 4–8 pallet spaces to the line.
  6. The customer’s warehouse scans the codes, and the delivery is recorded in its system in such a way that, once unloaded from the vehicle, the product can be passed straight to production. This limits costs on the customer’s side.

This cycle applies to all SKUs covered by the just-in-time arrangements, both those from stock and those made to order, thanks to the sheet stock we hold and the clear instructions in every production order. For standard made-to-size orders, without such arrangements, the usual lead time is 7 days (max. 16 working days). More about regular deliveries: delivery models with call-off stock held at the supplier.

What did not work the first time

A low box in thick BC board. One of the SKUs was a low box in thick BC board with two creases close together. The narrow panel between the creases made the box hard to close, and the first samples, made without creasing matrices, did not pass approval. A creasing matrix (counter-crease) is a groove (channel), matched to the board thickness, on the opposite side of the sheet, into which the creasing rule presses the board; thanks to it, the fold forms along the intended line. We bought a machine that works with creasing matrices, and the samples made with creasing matrices were approved.

Labels and WZ delivery notes. The first labels carried only our order number and our SKU number. The customer also needed its own order number and its own product number on them, so we added them in line with its order. Once further barcodes had been added, the labels and delivery notes carried so much information that handheld scanners had trouble reading them: many codes lay side by side. We implemented unique, definable print templates for the customer, which solved the problem.

Taking over in stages, without burning bridges

The customer did not hand volume over to us piece by piece, but whole SKUs, gradually. We started with the problematic SKUs, and with the rest we waited until the incumbent supplier had sold off its own stock, so as not to leave it with goods on its hands. The incumbent supplier serves the SKUs that have not yet moved to us. As a result one supplier is responsible for each SKU, and the change did not require a hard cut-over. We describe the staged model in our guide to switching box supplier step by step.

Results (status as at November 2026)

  • Deliveries arrive without delays.
  • The customer has not raised a single complaint since deliveries began.
  • Thanks to just-in-time deliveries the customer ran down its own buffer of boxes and gave up the rented warehouse.

We do not disclose prices or the number of SKUs taken over so far.

What this means for the purchasing department

  1. Split the SKUs into two groups. Items with higher consumption deserve a stock of finished boxes, while rarely used ones are better made to order from a stock of raw material.
  2. Start with the problematic SKUs. With the rest, let the incumbent supplier sell off its own stock: you do not burn bridges, and if needed you still have a second source (a second box supplier).
  3. Transfer whole SKUs, not fractions of the volume. One supplier is then responsible for each SKU.
  4. Before the first delivery, collect a full set of evidence for each SKU: reference samples, measurement report, inspection sheet and sign-off.
  5. Automate the documents. Reading orders from PDFs, WZ delivery notes with barcodes and labels with order numbers speed up the work of the customer’s warehouse.
  6. Align the loading sequence with the production plan. The product goes from the vehicle straight to the line.
  7. Meet the customer’s minimum requirements before the audit. Quality assessment, the methods of assessing it and the complaints register should be working before the supplier is audited.
  8. Test the labels and WZ delivery notes on the customer’s scanners. The customer’s own order and product numbers must be on the documents from the first delivery, and too many codes side by side make handheld scanning difficult; a print template defined together with the customer helps.
  9. Plan trials for unusual designs. A low box in thick board with a narrow panel between the creases may require a change of technology, for example creasing matrices, as early as after the first samples.

Frequently asked questions

When changing box supplier, do all SKUs have to be moved at once?

No. In the cooperation described, the customer hands whole SKUs over to us, one after another, and the incumbent supplier serves those that have not yet moved to us. We started with the problematic SKUs.

What about SKUs with a very low annual volume?

We do not stock them as finished boxes. We produce them after receiving an order, from a stock of board sheets managed by our system. Every production order contains clear production instructions.

What does product approval to VDA look like?

For each SKU: reference samples, measurement report, inspection sheet and sign-off before the first delivery. VDA is a method of auditing and assessing a supplier, not a certificate.

How does integration with the customer’s SAP work?

Orders from SAP arrive by email as PDF files and are read automatically. We generate WZ delivery notes with barcodes, plus pallet and product labels with the customer’s order numbers, which the customer’s warehouse scans automatically. We send accounting documents by email and via KSeF.

How quickly do you deliver orders?

For SKUs covered by the just-in-time arrangements, an order placed in the morning is fulfilled the same day and delivered the next morning, both for SKUs from stock and for those made to order. For standard made-to-size orders the usual lead time is 7 days (max. 16 working days).

What do deliveries to the production line look like?

One run a day by our own vehicle, 4–8 pallet spaces, in the sequence that follows the customer’s production plan. Delivery terms for other customers are agreed individually.

What did not work the first time?

Two things. The first samples of a low box in thick BC board with two creases close together, made without creasing matrices, were hard to close and did not pass approval; after we bought a machine that works with creasing matrices, the samples were approved. The first labels lacked the customer’s order number and product number, and once further codes had been added handheld scanners had trouble reading them, so we implemented unique, definable print templates for the customer.

See also the second case study from our practice: boxes for an automotive online shop – stock at the manufacturer with 24 h call-off, the third: corrugated inserts instead of foam at an electronics manufacturer, and the fourth – can trays for a pet food manufacturer from Lublin.

Changing or adding a box supplier?

Send us a sample, a photo with dimensions or a list of boxes, and we will prepare a quotation within a few hours. We present the plan, schedule and steps at the earliest possible date. See also: switching box supplier step by step and packaging for manufacturers – B2B cooperation. You can also use the price calculator for custom-size boxes, call +48 81 440 53 65 or write to kontakt@kartoniki.pl.